Building and Property Update week 2

Hey everybody here is a week 2 (11/14/14) property update…

The end of last week was spent stripping all the top soil and making rock piles.

The beginning of this week was spent flattening the high spots and raising up the low spots.  You’ll see in a couple of the pics they filled in the low area on the front of the property closest to 188.  That section still needs another 4-6 foot of fill to bring it up to the needed parking lot level. There will be a retaining wall here.

They also started exploratory digging where the building itself will be (foundation). So far they have not found anything they can't work with. No need for blasting so far. Good news!